How to Price a Stud Wall per m²: From Takeoff to Order List and Estimate

How to Price a Stud Wall per m²: From Takeoff to Order List and Estimate

Building in feet and inches? Read the US imperial version, priced per square foot.


If you can work out what goes into one square metre of wall, you can price the whole job. You don't need a QS for that. You need the right formula once, and a tool that does the counting every time after.


This post walks through the full process, the way I'd do it on site. First we work out a 100x50 stud wall per m² by hand, with a short roofing example after it. Then we turn that into an assembly in Assemble. After that we measure the drawings, and finally Assemble gives us the order list and a draft estimate.


All prices are indicative Irish trade rates in euro, ex VAT. Swap in your own supplier prices and your own labour rates. Those are the numbers that win you work. UK readers: the quantities are identical, just use your £ rates.


Step 1: Work out stud wall framing per m²


A 100x50 stud wall at 400 c/c and 2.4 m high needs 4.125 lm of timber per m², waste included. Here's where that number comes from.


The setup. A standard internal partition has:


  • 100x50 C16 treated studs at 400 c/c

  • A single head plate and a single sole plate

  • One row of noggins at mid-height

  • 10% waste, which also covers end studs and the trimmers around openings


Why per m²? Studs don't care how tall the wall is. At 400 c/c you always get 1 ÷ 0.4 = 2.5 lm of stud per m². Plates do care, because they run along the length of the wall. On a taller wall the same plates are spread over more square metres. The swing is only a few percent, so lock in a typical height (2.4 m) and keep a separate assembly for tall walls.


The formula. With H as wall height and c as stud centres:


Timber per m² = (1 ÷ c + 2 ÷ H + noggin rows ÷ H) × 1.10


At c = 0.4 and H = 2.4, that's (2.5 + 0.833 + 0.417) × 1.10 = 4.125 lm per m².


Fixings and labour. Plate fixings at 600 c/c on two plates come to 3.33 per lm of wall, or 1.389 per m². A carpenter sets out and frames about 1 lm of 2.4 m wall in half an hour, so 0.208 hr per m².


Item

Type

Qty per m²

Unit

Rate (€)

Cost (€)

100x50 C16 treated timber

Material

4.125

m

2.70

11.14

Frame fixings, head and sole plate

Material

1.389

each

0.40

0.56

90mm ring shank nails

Material

0.07

kg

4.50

0.31

DPC strip under sole plate

Material

0.417

m

0.27

0.11

Carpenter, set out and frame

Labour

0.208

hr

45.00

9.36

Total per m²





21.48


That's €12.12 of materials and €9.36 of labour per m² of wall. If you work at 600 c/c, the stud figure drops to 1.667 lm per m² and the total comes down with it.


The same logic for roofing


Roofs work the same way, with one extra number: the pitch factor. Drawings show the roof on plan, but you build it on the slope. A slope is always bigger than its plan area.


Slope area = plan area ÷ cos(pitch)


At 35° the factor is 1 ÷ cos 35° = 1.221. So 100 m² on plan is 122.1 m² on the slope.


The cleanest approach is to build your roofing assembly per m² of slope. Then let the takeoff handle the pitch, which we'll get to in Step 3. That way one assembly works for every pitch you'll ever price.


Per m² of slope, for a cut roof at 400 c/c with concrete tiles at a 345 mm batten gauge:


Item

Formula

Qty per m² of slope

Unit

Rafters

1 ÷ 0.4 × 1.10 waste

2.75

m

50x25 treated battens

1 ÷ 0.345 × 1.10 waste

3.19

m

Breathable membrane

1.0 + 15% laps

1.15

m²

Carpenter, cut and fix

Your own output rate

per your crew

hr


Ridge, hips, valleys and fascia run by the metre, so give them their own per-lm assemblies. Don't bury them in the m² rate.


Step 2: Build it as an assembly in Assemble


An assembly is your per-m² calculation, saved once and reused on every job. Build it once and you never work out stud wall framing by hand again.


  1. Go to Assemblies and click Create assembly.

  2. Name it clearly, for example "100x50 Stud Wall, 400 c/c, framing". Add a category like "Walls" so it's easy to find later.

  3. Set the Tool to Area and the Assembly unit to m². This tells Assemble the assembly gets measured as an area on the drawings.

  4. Pick a colour. Every measurement you draw with this assembly shows up in that colour, so walls, roofs and floors are easy to tell apart on the plan.

  5. Add one component per line from the table in Step 1. For each one, set the name, the cost type (MAT for materials, LAB for labour), the unit, the quantity per m² and the unit cost.

  6. Check the assembly rate at the top matches your hand calc. For our wall that's €21.48 per m².


A few tips from building these:


  • Enter the worked-out number, not the formula. Assemble stores a fixed quantity per m², so put in 4.125, not "(2.5 + 0.833 + 0.417) × 1.10". Keep the formula in the description so you remember where it came from.

  • Use pack units for tiny prices. Unit costs round to two decimals. A screw at €0.015 becomes €0.02, so price by the box of 100 instead.

  • Keep labour on its own lines. Splitting materials from labour means the order list only shows what you need to buy, and your estimate still shows the full cost.

  • Make variants, not compromises. A 600 c/c version, a tall-wall version and a "framing plus board both sides" version are each worth their own assembly.


Step 3: Measure the drawings with takeoff


With the assembly built, measuring is just tracing the walls on the plan. Assemble does the multiplication. If you're new to measuring walls off drawings, our guide on how to do a framing takeoff covers it in more detail.


  1. Create a project and upload the drawings (PDF works fine).

  2. Set the scale on each sheet. Check it against a dimension you trust, like an overall building length, before you measure anything.

  3. Pick your stud wall assembly and trace each run of partition along its centre line. Clicking corner to corner along a run is quicker than drawing separate lines.

  4. Enter the wall height (2.4 m). Assemble turns each run you draw into an area: length × height = m² of wall.

  5. Name your runs ("Ground floor partitions", "Bedroom 2 wall") so the takeoff is easy to check later.


Worked example. Say the ground floor has 42 lm of new partition. At 2.4 m high, that's 42 × 2.4 = 100.8 m² of stud wall.


For roofs, measure the roof on plan as an area and enter the pitch (for example 35°, or 7:12). Assemble applies the pitch factor for you. That's why building the roofing assembly per m² of slope works so well: you measure what the drawing shows, and the slope area comes out right.


A note on openings: for framing, a door opening still needs a head, trimmers and cripples. Most builders don't deduct openings from stud wall framing. The 10% allowance covers the extra timber around them.


Step 4: Get the full order list


The order list takes every measurement on the job and multiplies it through your assemblies. You get one list of everything to buy. For our 100.8 m² of wall:


Material

Per m²

× 100.8 m²

Unit

Value (€)

100x50 C16 treated timber

4.125

415.8

m

1,122.66

Frame fixings

1.389

140

each

56.00

90mm ring shank nails

0.07

7.06

kg

31.75

DPC strip

0.417

42.0

m

11.35

Materials total




1,221.76


Labour lines stay off the order list, because you don't buy hours from the merchant. They show up in the estimate instead.


The order list shows each item's measured quantity, the quantity to order, its rate and value, and whether it's been ordered yet. If you buy timber in 4.8 m lengths, 415.8 lm is 86.6 lengths, so order 87.


Once the job has walls, floors and a roof measured, the same timber shows up across all of them in one list. That's the list you send to the merchant for a price, and the one you tick off as deliveries land. If the takeoff changes after you've built the estimate, Assemble flags that the estimate is behind, so nothing gets missed.


Step 5: Turn the takeoff into a draft estimate


The estimate is built straight from your measurements, so the numbers you priced are the numbers you measured. Create the estimate from the takeoff and Assemble brings in every measured assembly, with materials and labour.


For the stud wall example:


Line

Quantity

Cost (€)

Stud wall materials

100.8 m²

1,221.76

Carpenter, set out and frame

20.97 hr

943.49

Stud walls total, ex VAT

100.8 m²

2,165.25


From there, the draft is yours to finish:


  • Add your margin and any preliminaries, like skips, scaffold or site setup.

  • Add one-off lines by hand, such as "Remove existing stud wall". Hand-added lines stay put when you refresh.

  • If the drawings change, re-measure and use Refresh from Measurements. Quantities update from the new takeoff, and your hand-added lines are left alone.

  • Export it as a PDF for the client when you're happy with it.


Do the maths once


It takes about ten minutes to work out one square metre of wall properly and save it as an assembly. After that, every job is just measuring: trace the walls, get the order list, and have a draft estimate ready before the kettle boils.


Start with the assembly you price most often. For most of us that's a stud wall or a cut roof. Build it with your own rates, then measure your next job with it and check it against how you'd normally price that job. Once the numbers line up, you'll trust it on every job after.


You don't have to set it up on your own. The Assemble team will help you get a new account up and running and build your first assemblies with you. Send us your rates, your price list, or how you price a stud wall today, and we'll turn it into assemblies that are ready for your next takeoff.


Frequently asked questions


How much timber is in a square metre of stud wall?


A 100x50 stud wall at 400 c/c and 2.4 m high needs about 4.125 lm of timber per m², including 10% waste. That is 2.5 lm of studs, 0.833 lm of head and sole plate and 0.417 lm of noggins, plus the waste allowance.


How much does a stud wall cost per m²?


At indicative Irish trade rates, a 100x50 C16 stud wall at 400 c/c comes to about €21.48 per m² ex VAT: €12.12 of materials and €9.36 of labour. UK builders can use the same quantities with their own £ rates.


How do you convert a roof plan area to slope area?


Multiply the plan area by 1 ÷ cos(pitch). At 35° the factor is 1.221, so 100 m² on plan is 122.1 m² on the slope.


Should you deduct door openings from stud wall framing?


Usually not. A door opening still needs a head, trimmers and cripples, and the 10% waste allowance covers the extra timber around openings.


How many 4.8 m lengths of timber do I need for a stud wall?


Multiply the wall area by 4.125 lm per m², divide by 4.8 and round up. For 100.8 m² of wall that is 415.8 lm, or 86.6 lengths, so order 87.

Assemble cover: price framing and roofing from m² to estimate, showing a 100x50 stud wall assembly at €21.48 per m², an order list and a draft estimate
>